The FY 2000 Budget Request for Major
Research Equipment (MRE) is $85.0 million, a decrease of $5.0 million, or 5.6
percent below the FY 1999 Current Plan of $90.0 million.
(Millions of
Dollars)
The Major Research Equipment account
was established in FY 1995 to provide funding for the construction and
acquisition of major research facilities that provide unique capabilities at
the cutting edge of science and engineering. Projects supported by this account
are intended to expand the boundaries of technology and will offer significant
new research opportunities, frequently in totally new directions, for the
science and engineering community. Operations
and maintenance costs of the facilities are provided through the Research and
Related Activities (R&RA) account.
In FY 2000, funding for six projects is requested
through the Major Research Equipment account: the Large Hadron Collider (LHC),
the Millimeter Array (MMA), the Network for Earthquake Engineering Simulation
(NEES), Terascale Computing Systems, Polar Support Aircraft Upgrades and the
modernization of South Pole Station.
Funding for MRE projects is summarized
below:
(Millions of
Dollars)
1 In FY 1998, $34.67 million was carried over into FY 1999,
largely in support of the South Pole Station Modernization Project.
LARGE
HADRON COLLIDER
The FY 2000 Request for construction of
the Large Hadron Collider (LHC) detectors, A Toroidal Large Angle Spectrometer
(ATLAS) and Compact Muon Solenoid (CMS), is $15.90 million. To complete the project, this Budget
requests advanced appropriations of $16.4 million in FY 2001, $16.9 million in
FY 2002, and $9.7 million in 2003.
Total NSF funding for this project is $80.90 million over the period FY
1999-2003. Oversight of this project is
provided through the Physics Subactivity within the Mathematical and Physical
Sciences (MPS) Activity.
Funding for the overall LHC project,
including both the detectors and the accelerator, will be provided through an
international partnership involving NSF,
Department of Energy (DOE), and the CERN member states, with CERN member
states providing the major portion. The
total U.S. contribution will be $531.0 million, including $450.0 through the
DOE. NSF and DOE will jointly provide a
total of $331.0 million for the detector construction, while DOE will provide
sole U.S. support ($200 million) for the accelerator construction.
The
LHC will be constructed at the CERN laboratory in Switzerland. The facility will consist of a
superconducting particle accelerator providing two counter-rotating beams of
protons, each with energies up to 7 TeV (7x1012 electron
volts). Two detectors, ATLAS and CMS,
will be constructed to characterize the reaction products produced in the very
high energy proton-proton collisions which will occur at intersection regions
where the two beams are brought together.
The LHC will enable a search for the Higgs particle, the existence and
properties of which will provide a deeper understanding of the origin of mass
of the known elementary particles. The
LHC will also enable a search for particles predicted by a powerful theoretical
framework known as supersymmetry which will provide clues as to how the four known
forces evolved from different aspects of the same “unified” force in the early
universe.
The two LHC detectors will provide
partially redundant and partially complementary information aimed at maximizing
the chance of discovery. Both detectors
will operate at extremely high data rates, which will push the state-of-the-art
technology of electronic triggers, data acquisition, and data analysis.
Construction
funding for the ATLAS and CMS detectors is scheduled to be completed in FY
2003. The overall LHC construction,
including both the accelerator and the ATLAS and CMS detectors, is scheduled
for completion in FY 2005.
NSF Support For LHC
(Millions of
Dollars)
NOTE: Total may not add due to rounding.
Milestones for
the LHC are outlined below:
FY 2000 Milestones
US ATLAS:
Complete design for tracking and calorimetry readout, complete design of
calorimeter triggers, complete production of muon chamber electronics.
US CMS: Ship
calorimeter supports to CERN, start design of tracking electronics.
FY 2001 Milestones
US ATLAS: Ship
calorimeter cryostat to CERN, complete calorimeter feedthrough and electronics production, complete muon
chamber support structures, complete trigger prototypes.
US CMS: Finish
design of tracking electronics, complete production of muon chambers, finish
production of optical system for calorimeters.
FY 2002 Milestones
US ATLAS: Complete tracking module production, complete
transition radiator production, complete calorimeter production and start
installation, start trigger installation.
US CMS: Complete calorimeter electronics and ship to CERN,
start data acquisition system assembly.
FY 2003 Milestones
US ATLAS: Complete muon chamber production, start
installation, complete transition chamber electronics
US CMS: Install muon chambers, complete data acquisition
system, complete photodiode production, test detector magnets.
FY 2004 Milestones
US
ATLAS: Complete tracking read out installation, complete calorimeter
installation, complete muon chamber alignment, complete trigger installation,
complete transition chamber installation.
US
CMS: Install detector magnets, ship calorimeter tracking elements to CERN,
complete all construction.
FY 2005 Milestones
Initiate and complete commissioning of ATLAS and CMS
detectors. (Coincides with scheduled
completion of construction of the LHC accelerator by the end of the year.)
MILLIMETER
ARRAY
The Millimeter Array (MMA) will be an aperture-synthesis radio
telescope operating in the wavelength range from 3 to 0.4 mm. The Array is planned to consist of 36
10-meter diameter radio telescopes.
These will be located at the
same site and electronically linked.
The MMA will be the world's most sensitive, highest resolution,
millimeter-wavelength telescope. It
will combine an angular resolution comparable to that of the Hubble Space
Telescope with the sensitivity of a single antenna more than fifty meters in
diameter. The MMA will
provide a testing ground for theories of star birth and stellar evolution,
galaxy formation and evolution, and the evolution of the universe itself. The MMA will reveal the inner workings of
the central black hole “engines” which power quasars, and will make possible a
search for earth-like planets around hundreds of nearby stars.
Funding for the three-year Design and Development Phase of the MMA project will total $26.0 million, including a requested $8.0 million in FY 2000. Total costs for the MMA project are estimated to be approximately $230.0 million. International or other-agency participation at the 25-50% level is being actively sought for the project. Funding for the 5-year capital construction phase will be requested only after appropriate review and approval by the National Science Board.
During the Design and Development Phase of the project, a prototype
antenna will be constructed, a digital correlator architecture chosen,
international and agency partners identified. Discussions with a European
consortium to form a partnership between the U.S. and a number of European
institutions are underway.
NSF Support For MMA Design And Development
(Millions of
Dollars)
Milestones for
the MMA are outlined below:
FY 1998 Milestones (accomplished):
Design antenna;
Select MMA site;
Begin negotiations with possible international partners;
Design and begin construction of prototype receivers;
Design prototype correlator, computer/software system, LO and fiber
optic systems.
FY 1999 Milestones:
Complete first prototype receiver components;
Select prototype antenna contractor;
Select local oscillator system.
FY 2000 Milestones:
Deliver prototype antenna to U.S. test site;
Begin antenna 1 single dish testing;
Finalize agreements with international partners;
Deliver prototype correlator and receivers to test site.
Following the Design and Development phase, NSF will decide whether to
proceed to the second phase, a five-year Capital Construction Phase. This
two-step process will enable NSF to evaluate the project before undertaking
major expenditures.
Network for Earthquake Engineering Simulation
The FY 2000 Request to initiate construction of the Network for Earthquake Engineering Simulation (NEES) is $7.70 million. To complete this project, this Budget requests advanced appropriations of $28.20 million in FY 2001, $24.40 million in FY 2002, $4.50 million in FY 2003, and $17.0 million in FY 2004. Total NSF funding for this project, including both the experimental facilities and the network, is $81.90 million over the period FY 2000-2004. Oversight of this project will be provided through the Civil and Mechanical Systems Subactivity within the Engineering (ENG) Activity.
The Network will be
developed to include geographically distributed and network-interconnected
physical facilities constructed under cooperative agreements with NSF. The NEES project will upgrade, modernize,
expand and network major facilities including:
(a) shake tables used for earthquake simulations; (b) large reaction
walls for pseudo-dynamic testing; (c) centrifuges for testing soils under
earthquake loading; and (d) field testing facilities.
The NEES project will
transform earthquake engineering research from its current reliance on physical
experiments to investigations based on integrated models, databases and
model-based simulation. The NEES
project will exploit Internet technology to integrate and interconnect these
nationally distributed facilities with a computer network to afford remote
access. The NEES network will provide interoperability, resource sharing,
scalable and efficient net-wide deployment, open-system standardization,
database consistency and integrity, and modularity in both software and
hardware architectures.
Construction funding for
the NEES physical facilities and network integration is scheduled to be
completed in FY 2004. When NEES is
completed, it will be operated by a consortium that includes participation from
host institutions, affiliate organizations, and the user community. Beyond FY 2004, the annual operations and
management budget for NEES will be approximately $8 million.
NSF Support For NEES
(Millions of
Dollars)
NOTE: Total may not add due to rounding.
Milestones for the NEES are outlined below:
FY
2000 Milestones
Initiate and complete
construction of multi-degree of freedom test system, soils laboratory, and
shake table upgrade;
Begin development of system
architecture and planning for integration and interface design.
FY
2001 Milestones
Initiate construction of
new shake table, response modification device, mobile structural test facility;
Initiate and complete
construction of ground motion simulator and post-quake mobile laboratory;
Continuation of network
software and hardware implementation.
FY
2002 Milestones
Continue construction from
FY 2001 and initiate construction of upgrades for NEES centrifuge and tsunami
tank, three-dimensional reaction wall, pseudo-dynamic laboratory, mobile
seismic wave source, and development of field sites;
Initiate and complete
construction of high capacity load simulator;
Establish site connections
for system integration.
FY
2003 Milestones
Complete construction from
FY2002;
Complete equipment
calibration of new shake table;
Initiate system integration
test bed operations.
FY
2004 Milestones
Complete construction and
calibration of facilities from FY2003, complete additional upgrade of one shake
table, complete construction of one- and two-dimensional centrifuge shakers;
Complete testing of system
integration test bed operations.
FY
2005 Milestones
All components operational
and calibrated;
Networking and interfaces
completed;
Complete commissioning of
the NEES facilities and network.
POLAR SUPPORT AIRCRAFT UPGRADES
Ski-equipped LC-130 aircraft are the backbone of the U.S. Antarctic Program’s (USAP) air transport. LC-130’s also support NSF’s research in the Arctic. The Air National Guard (ANG) is in the process of assuming operational control of all LC-130’s and, by March 1999, will provide the sole LC-130 support to the USAP. The ANG has six LC-130’s and also flies one NSF-owned aircraft recently acquired. Three additional NSF-owned LC-130’s require upgrades and modifications to meet Air Force safety and operability standards. NSF reviewed whether the polar mission could be supported with nine rather than ten LC-130’s. That review was ongoing at the time the FY 1999 NSF Request was being prepared, and the FY 1999 NSF Request included $20 million in the Major Research Equipment Account for aircraft upgrades.
The analysis of aircraft requirements requested by NSF focused on mission requirements and maintenance. During the austral summer, six LC-130’s will be “in theater” in New Zealand or Antarctica, and four LC-130’s will be at the ANG’s base in Scotia, New York, for missions in Greenland, other Department of Defense requirements, New York state requirements, training missions, or maintenance.
The ANG mission has five major components: Antarctic support, Arctic support (including Department of Defense Arctic interests), training (for defense readiness and aircraft qualification), national response, and New York state response requirements. The ANG analysis of aircraft requirements used an Air Force computer model to determine aircraft needs. The model takes into account, among other parameters, the number of flight hours required for all missions. This includes crew qualifications for the ANG wartime mission, adding the USAP mission and training for added crews, and downtime for maintenance. The ANG’s current mission requires approximately 4000 flight hours annually. Support of the USAP will add an additional 4000 flight hours annually.
The results of the Air Force model clearly support the need for a total of 10 LC-130’s, and NSF concurs that a third aircraft needs to be modified in order to support the Foundation’s polar missions. The FY 2000 Request includes $12 million to complete the upgrades to the NSF-owned aircraft.
The current budget profile to complete the upgrades is below:
Support for Aircraft Upgrades
(Millions of Dollars)
1
Engineering costs of $800,000 in
FY 1998 and $3.2 million in FY 1999
were funded through the U.S .Polar Research Programs Activity of the
R&RA Account. Upgrade project costs
of $20 million were provided through the MRE Account, for a FY 1999 total of
$23.2 million.
The estimated cost includes engineering, avionics,
airframe, safety, propulsion, electronics and communications, equipment for
black box installation, storage, and project administration.
A competitive contract for the modifications will be awarded and administered by the Air Logistics Command at Robins Air Force Base (Warner Robins, GA). NSF’s Office of Polar Programs will work with the project managers to approve, fund and track the progress of the work, to ensure the modifications are completed on schedule by FY 2001.
The South Pole is of particular
geopolitical significance due to its location at the convergence of the
territorial claims of six of the Antarctic Treaty nations. NSF-supported activity achieves the foreign
policy objective of maintaining U.S. presence in Antarctica, while providing an
observatory for several fields of science.
The scientific opportunities are unique as a result of the particular
geophysical conditions at the South Pole.
Because of its
location on an ice sheet at Earth's axis of rotation, its altitude and cold dry
atmosphere, six-month-long days and nights, and its remoteness from centers of
human population, the station at the South Pole has important advantages for
conducting world-leading science in areas such as infrared and submillimeter
astronomy, the study of seismic and atmospheric waves, and research on
long-term effects of human activities on the atmosphere.
The United States
Antarctic Program (USAP) External Panel, convened in October 1996, examined
infrastructure, management, and science options for USAP, including
consideration of South Pole Station.
The Panel noted that funds specifically appropriated in FY 1997 (South
Pole Safety Project) would rectify the most extreme safety, health and
environmental concerns at the South Pole, but did not address the underlying
problems of aging facilities in a life-threatening environment. They also stated that further life-extension
efforts devoted to the existing South Pole facility were not cost effective,
and recommended that the station be replaced.
Based on this recommendation, the South Pole Station Modernization
project was initiated.
SOUTH
POLE STATION MODERNIZATION
The goals of South Pole Station
Modernization (SPSM) are:
·
Maintain a U.S. presence in accordance with national policy
·
Provide a safe working and living environment
·
Provide a platform for science
·
Achieve a 25-year station life
In FY 1998, $70.0 million was
appropriated to begin the South Pole Station Modernization project, and in FY
1999 a second increment of $39.0 million was appropriated. The FY 2000 Request
includes $5.4 million for the next phase of the project. This Budget includes
an advanced appropriations request of $13.50 million in FY 2001 to complete the
project. Priorities in implementing the
modernization project include increasing safety, minimizing environmental
impacts and disruption of ongoing science, and optimizing the use of existing
facilities during the modernization.
The USAP External Panel’s Optimized Station model was the basis for Congressional discussions leading to the FY 1998 appropriation. The Optimized Station is an elevated station complex with two connected buildings, supporting 110 people (46 science personnel and 64 support personnel) in the summer, and 50 people (31 science personnel and 19 support personnel) in the winter. The cost estimate for the Optimized Station is $127.9 million.
The
current budget profile for the Optimized Station is below:
(Millions of
Dollars)
The estimates
include materials, labor, logistics for transportation of all material and
personnel to the South Pole, construction support, inspection, and equipment,
as well as demolition and disposal. The
location at the South Pole requires significant lead time for construction
projects because of the long procurement cycle, the shipping constraints (one
vessel per year to deliver materials), and the shortened period for
construction at the South Pole (100 days per year). Construction is anticipated to begin in FY 2001 and to be
completed by FY 2005. The project is
currently on budget and on schedule.
SPSM Milestones
Activity |
Funding |
Transport to Antarctica |
Airlift to South Pole |
Start Construction |
Finish |
Vertical Circular
Tower |
FY98 |
FY99 |
FY00 |
FY00 |
FY02 |
Quarters/Galley |
FY98 |
FY99/00 |
FY00/FY01 |
FY01 |
FY02 |
Sewer Outfall |
FY98 |
FY99 |
FY00 |
FY01 |
FY01 |
Fuel Storage (100K
gallons) |
FY98 |
FY98 |
FY99 |
FY99 |
FY99 |
Medical/Science |
FY98 |
FY99/00 |
FY00/01 |
FY02 |
FY03 |
Science Lab/
Communications/Administration |
FY98 |
FY00 |
FY01 |
FY02 |
FY03 |
Dark Sector Lab |
FY98 |
FY99/00 |
FY00/01 |
FY02 |
FY03 |
Water Well |
FY98 |
FY99 |
FY00 |
FY01 |
FY02 |
Data
Transmission/Communications (RF) Building |
FY98 |
FY00 |
FY01 |
FY02 |
FY03 |
Emergency
Power/Quarters |
FY99 |
FY01 |
FY02 |
FY03 |
FY04 |
Liquid nitrogen and
helium |
FY99 |
FY01 |
FY02 |
FY03 |
FY03 |
Quarters/Multipurpose
Area |
FY99 |
FY02 |
FY03 |
FY04 |
FY05 |
Warehousing, SEH
and Waste Management |
FY99 |
FY03 |
FY04 |
FY05 |
FY05 |
Station Equipment |
FY99 |
FY03 |
FY04 |
|
FY04 |
Electronic Systems
and Communications |
FY00/01 |
FY00/01 |
FY01/02 |
FY03 |
FY04 |
Contingency
The current cost estimate includes several factors to account for the uncertainties and risks inherent in the project. The cost estimate includes a $6 million contingency for loss or damage to materials during shipping. The cost estimate also includes a location factor for labor at the South Pole: the initial estimate for labor at the South Pole was multiplied by 2.6 to account for the uncertainties of weather and logistics at such a remote location. This multiplier is based on previous experience on construction projects at the South Pole.
The project estimate used by the USAP
External Panel in its recommendations did not include any cost contingency
provision, although it noted that this represents a departure from commercial
practices. Commercial construction
projects usually include a contingency for cost variances between the design
and planning phases of a project and award of the final construction
contract. This contingency varies
depending on the phase of the project and the reliability of cost
estimates. For example, at the
preliminary working drawing stage, a contingency of 10 percent would be added
to the cost estimate; at the final working drawing stage, a contingency of 2
percent would be added to the cost estimate. SPSM is currently between those
two phases. Adding a contingency for cost variance at this stage would add
approximately $10.2 million to the total estimate for South Pole Station
Modernization.
Also, a contingency for uncertainties
in logistics costs -- market-driven fuel cost increases; aircraft maintenance
and repair uncertainties -- would add an additional $1.3 million (based on an
analysis of logistics costs during the 1983-1993 period).
SOUTH POLE SAFETY PROJECT
Funding was
provided in FY 1997 to address urgent and critical safety and environmental
concerns at Amundsen-Scott South Pole Station. A total of $25.0 million was
provided for improvements to the heavy equipment maintenance facility, the
power plant, and the fuel storage facilities. Milestones for each component are
below. The project is scheduled to be operational by FY 2002. The project is currently on budget and on
schedule.
Milestones
Activity |
Funding/ Procurement |
Transport to Antarctica |
Airlift to South Pole |
Start Construction |
Finish |
Heavy Equipment
Maintenance Facility Arch |
FY97 |
FY97 |
FY97/FY98 |
FY98 |
FY98 |
Heavy Equipment
Maintenance Facility Building |
FY97 |
FY98 |
FY98/FY99 |
FY00 |
FY00 |
Power Plant Arch
and Building |
FY97 |
FY98 |
FY99 |
FY00 |
FY01 |
Fuel Storage System |
FY97 |
FY98 |
FY98/FY99 |
FY99 |
FY99 |
There is growing recognition that information technology, particularly computational simulation and modeling is a key contributor to United States economic growth and competitiveness, defense capabilities, environmental studies, and climatology, and scientific and engineering research. Over the past decade, simulation and modeling of a vast array of scientific, engineering and mathematical problems have led to revolutionary scientific insights. All signs indicate that progress here is accelerating. Moreover, new application domains that are ripe for exploration, such as intelligent data mining and crisis management, are continually being identified.
For over a
decade, NSF has led all Federal agencies in providing high-performance
computing systems and networks to the nation's academic science and engineering
communities. Beginning in FY 1998, this computational infrastructure is
provided through the Partnerships for an Advanced Computational Infrastructure
(PACI). More than 60 geographically
distributed partner institutions from 27 states and the District of Columbia
are associated with PACI.
The Information
Technology for the 21st Century (IT2) Initiative will
provide access to terascale computing resources for the science and engineering
community. Such access to leading edge computing capabilities and advanced
computing research is critical to maintaining the nation’s leading edge and to
educating the next generation of computer and computational scientists.
As part of IT2,
the Terascale Computing Systems project will enable U.S. researchers to gain
access to leading edge computing capabilities.
The project will be connected to NSF’s existing PACI network, and will
be coordinated with other agencies’ activities, such as DOE’s, to leverage the
software, tools and technology investments, while ensuring a full and open
competition.
The Request
includes $36.0 million for the Terascale Computing Systems project in FY 2000
to put in place a 5-teraflop capability at one site. Additional funding will be
required to maintain state-of-the-art
facilities for this effort in FY 2001 and beyond.
The Gemini Telescopes Project is constructing two
8-meter telescopes, one in the northern and one in the southern hemisphere, in
Hawaii and Chile, respectively. The
Hawaiian telescope will be optimized for infrared observations. The Project is an international
collaboration with the United Kingdom, Canada, Australia, Chile, Argentina and
Brazil.
Capital construction costs provided for
this project by the U.S. have been $92.0 million, which represents 50 percent
of the total cost of the project. First
light on the Gemini North Telescope was achieved in December 1998. Some related
instrumentation developments have been delayed.
Astronomers need to resolve important
questions about the age and rate of expansion of the universe, its overall
topology, the epoch of galaxy formation, the evolution of galaxies once they
are formed, and the formation of stars and planetary systems. This new generation of optical/infrared
telescopes with significantly larger aperture (8-meter diameter) than existing
instruments will provide better sensitivity and spectral and spatial
resolution. Technological advances in a
number of key areas of telescope construction and design will allow these
instruments to take advantage of the best performance the atmosphere will
allow.
Milestones for Gemini, for both the
project and technological enhancements, are described below:
FY 1999 Milestones Enhancements
Accept first Instrument,
Hawaii; Complete
front surface heating;
Complete enclosure, Chile; IR wavefront
sensors procured
Deliver telescope
structure, Chile; Complete
coating plant site acceptance,
Complete polishing primary
mirror, Chile. Chile.
FY 2000 Milestones
Acceptance of control
system, Hawaii; Implement
mirror cleaning, Chile
Handover of operations,
Hawaii;
Install acquisition
guiding unit, Chile;
Install primary mirror,
Chile;
Install chopping secondary
assembly, Chile;
FIRST LIGHT, Chile.
FY 2001 Milestones
Final acceptance of first instrument, Chile;
Acceptance of control systems, Chile;
Hanover of operations, Chile.
LASER
INTERFEROMETER GRAVITATIONAL WAVE OBSERVATORY
Funding of the construction phase of
the The Laser Interferometer Gravitational Wave Observatory (LIGO) project was completed in FY 1998 at a total cost of $271.9
million. LIGO will be a national user
facility for research in gravitational physics, serving many U.S. faculty,
students, and other researchers. The
LIGO construction project is being carried out through a Caltech-MIT
collaboration. Construction of the major facilities at the two LIGO sites, one
at Hanford, Washington and one at Livingston Parish, Louisiana, is nearing
completion. Each LIGO detector is an
L-shaped interferometer, 4 km on a side.
Support for LIGO operations began in FY 1997, provided through the
Physics Subactivity of the Mathematical and Physics Sciences Activity. Operations support ramped up to $20.8
million in FY 1999. Additional support
of $2.3 million was provided for advanced R&D for improving the sensitivity
of LIGO as an astrophysical observatory.
The total funding for LIGO in FY 2000 is $23.7 million, of which $21.1
million is for operations.
The primary objectives of LIGO are to
detect gravitational waves, to test dynamical features of Einstein’s theory of
gravitation, and to study the properties of intense gravitational fields. LIGO will detect the passage of
gravitational radiation that originated from catastrophic stellar events such
as supernova, binary star coalescence, or possibly even echoes from the
formation of the universe itself. LIGO
thus represents a new observational window on the universe and stellar
phenomena. New gravity wave detectors, modeled after LIGO, are planned or are
under construction by a number of other countries, providing opportunities for
important international scientific cooperation.
Civil construction at both LIGO sites
is completed, including the large vacuum systems which contain the
interferometer. Contracts have been
awarded for the lasers and optical elements.
Delivery of optical elements and interferomenter installation began at
both sites in FY 1999. The overall
control system is at an advanced stage.
A final design review for critical elements, including the laser,
length-sensing and controls, alignment, and environmental monitors has been
completed. The project remains on
schedule and on budget, with first scientific observations planned for FY 2001.
NSF Support
For LIGO
(Millions of
Dollars)
1 Funded through
the Physics Subactivity within the R&RA account.
LIGO
Milestones are outlined below:
FY 2000 Milestones:
Begin
coincidence tests at both detector sites.
FY 2001 Milestones:
Begin
scientific observations at both detector sites.